75 Executive Villas

Construction of 75 new two, three and four bed executive villas including infrastructure.

Key Features of the Project

  • 20% reduction of original programme from 40 to 32 weeks
  • Use of the innovative TEK Haus Building System
  • Partnering Approach
  • Supply Chain Partnering
  • Monthly Key Performance Indicators
  • Operating within a fully operational village

 

Client Comments:

We would like to express our thanks and satisfaction with the service provided by Robert Woodhead Limited on the above project. In particular we were delighted with Woodhead’s innovative introduction of the Kingspan TEK Haus System. This brought vastly improved U.value performance, sound reduction benefits and a room-in-a-roof solution for the 4 bed executive villas. Your team should also be congratulated on their adaptability in accelerating the programme. We appreciate all the hard work which was put in from your company and your supply chain. The finished product is one which both Center Parcs and myself are proud to be associated with, as I am sure you are. We look forward to working with Robert Woodhead Limited in the future to extend this presently successful relationship.

Maurice Edwards, Project Manager, Center Parcs Limited